Put a scope change in writing before doing the extra work

Write a change request that states the extra work, price, delivery date, and approval needed before the revised work begins.

Blank cardstock and folded place cards sit on a print studio counter.

A request for extra work can sound quick while you’re talking. Before you start, put it beside the current agreement and show the customer what it would change. Give them the price, timing, and a clear way to decide.

Describe the work the customer is asking to change

Find the most recent approved scope. Identify the deliverable, quantity, or deadline that would change. Then say exactly what you would add, remove, or substitute. If the customer uses a broad phrase such as more revisions, ask what they want to receive and how many review rounds they expect. Name anything they’ll need to provide and when it’s due.

Check the agreement for its change procedure and who has authority to approve. Some kinds of work have specific requirements. For California home improvement contracts, the Contractors State License Board explains that changes are made in writing and gives guidance on recording changes to work, price, and completion dates (California Contractors State License Board, checked November 21, 2026). Use the process and documents that apply to your work. Ask a qualified local attorney if you need help interpreting what the agreement requires.

Show the revised cost and ask for a clear answer

Include the original project or quote reference and the piece of work affected. State the price change and the new total. If any cost is still an estimate, say what could change it and how you’ll get approval. Compare the old and new delivery dates. Spell out what you’ll need from the customer before you can meet the new date.

Send the change to the person authorized to approve it, using the agreement’s process. If the client asks for a different version, update the request and mark which version it replaces. Save the approved scope alongside the original agreement so the people delivering and invoicing the work can use the same terms.

If more than one person is working on the job, share the approved version with them before they order materials or promise a new date. File the earlier version so you can tell which terms changed.

Two sizes of blank paper lie beside an empty card holder.

Illustrative example — Adding place cards to a print order

Suppose a client approved 100 printed menus for $420, due Thursday. They now ask for 50 place cards. In this example the original quote requires written approval for scope changes. It permits the client’s designated contact to approve by email. The client wants menus and cards delivered together.

Change request for the menu order
Add 50 printed place cards using the names you supply. The existing 100 menus stay in scope. The place cards add $85, bringing the total to $505. Delivery of both items would move from Thursday to Friday, provided we have the final name list and your written approval by noon Wednesday. Please reply by then to approve the place cards, new total, and Friday delivery.

If the client approves, save the reply and use the new total and date in the job record. If it misses the deadline, check which work can still go ahead and confirm the available delivery date before printing the place cards.

Common questions

Can I keep working while I wait?

If part of the original work can continue under the agreement, keep it separate from the extra work. If the change affects what you’re already making, tell the client what’s waiting on their answer and check the agreement before pausing any contracted work.

What if the person who asked can’t approve the price?

Ask them to connect you with the person who can. Send the same scope, price, and dates to that person so they can approve a specific version. If the client uses purchase orders, ask whether its order needs to change before you proceed.